March 2008

Upgrades in the Canyon

The Stone Canyon Water Quality Improvement Project has two goals: meeting tough federal surface-water regulations, and providing safe and reliable water to 400,000 Los Angeles residents.

Article Tools

Create a Link to this Article

By Dan Rafter

Comments


To submerge the pipe, workers slowly filled it with water. All the while, the crane supported the HDPE pipeline’s middle section. This allowed the workers to fill the pipe’s northern end with water first, so that the pipe would gradually submerge and move into its correct position on the
reservoir floor.

The process worked, but, it was not perfect, something not surprising considering the size and scope of the project. Terry Flinn, project manager with Underwater Resources Incorporated, in San Francisco, was intimately involved in the project. Underwater Resources actually built the 8,000-foot-plus pipeline used in the project.

Flinn had recommended that the ballast blocks attached to the HDPE pipeline be bottom-weighted to prevent rotation of the pipe before it was submerged. Other engineers disagreed, so the project continued without the weighted ballasts.

This meant that workers did struggle somewhat to keep the pipeline from rotating. But crewmembers did work around the problems and successfully completed the project, Flinn says.

“As you can understand, once you get into a remote location with rental equipment, it’s very difficult to stop work and wait for a resolution from a large general contractor who is waiting for direction from a large bureaucracy,” says Flinn. “We had to keep on moving ahead. We did the best we could, and I think it all went well.”

He says he and his company gained valuable experience from the Stone Canyon project. “It’s an interesting day once you decide it is submergence time,” he adds. “That is the critical time, when you’re pumping water in one end and letting air out the other through valves. That’s when the pipe is at its most vulnerable condition for kinking. That is the critical time in the whole operation. You have to get through that part as quickly as possible.”

Advertisement

Bentwood agrees with Wells that submerging the pipeline was the right way to go. To tunnel that distance would have not only cost more, it would have been more intrusive to neighbors. Considering that the Los Angeles Department of Water and Power had dedicated more than a decade to working with the surrounding communities on the project, it would have been a terrible waste to end up aggravating them with extensive digging and tunneling near their properties.

“The tunneling that we did have to do from a homeowner’s perspective was barely visible,” says Bentwood. “It was done mostly during the daylight hours, so there was very little lighting annoyance in the nighttime hours. There was no blasting. And then the lake-bottom pipeline we installed was probably very interesting to the neighbors who were able to watch it floating out there across the full length of the reservoir. It was a fascinating project. It was all very efficient, very well done.”  

Author's Bio: Dan Rafter is a technical writer in IL.

What Do You Think?

Post a Comment

Be the first to tell us what you think!

Post a Comment

Not a subscriber? Sign Up
 
 
*  
 




 

Get Water Efficiency Email Updates!

Get weekly news and updates through our Water Efficiency email newsletter!